New School Update

Over the last couple of weeks we have completed the steel frame which will create the skeleton for the building.  This now enables us to start the external walls; these will be built around the frame to form the external envelope.  We have also started forming the floor support slab.  This is a concrete slab 25cm thick and sits on the ground beams covering the whole floor.  This is not the finished floor level – it provides a support for the main flooring and internal walls.

 