Over the last couple of weeks we have completed the steel frame which will create the skeleton for the building. This now enables us to start the external walls; these will be built around the frame to form the external envelope. We have also started forming the floor support slab. This is a concrete slab 25cm thick and sits on the ground beams covering the whole floor. This is not the finished floor level – it provides a support for the main flooring and internal walls.